File #: 26-0280    Version: 1
Type: Resolution Status: Agenda Ready
File created: 4/23/2026 In control: City Council
On agenda: 5/18/2026 Final action:
Title: Adoption of a Resolution Authorizing the City Manager to Execute a Purchase Agreement with Spearus and Dell Technologies for Procurement and Deployment of Replacement Server and Storage Infrastructure for the City's Primary Data Center in the Amount of $362,402, plus a 35% Contingency of $126,840, for a Total Not-to-Exceed Authorization of $489,241.
Attachments: 1. Staff Report, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Adoption of a Resolution Authorizing the City Manager to Execute a Purchase Agreement with Spearus and Dell Technologies for Procurement and Deployment of Replacement Server and Storage Infrastructure for the City's Primary Data Center in the Amount of $362,402, plus a 35% Contingency of $126,840, for a Total Not-to-Exceed Authorization of $489,241.